Parking Garage at the Design Stage: Barriers, Ventilation, Payment and EV Charging, and What Must Be Decided Before the Pour

By Ofek Sela, VP Marketing · · 6 min read

A new underground car park with EV chargers, jet fans and an entry barrier
In this article 9 topics
  1. What has to be decided now, and what can wait?
  2. Electric vehicle charging: what is mandatory in Israel?
  3. Charging decisions worth making at design
  4. Fire safety in charging: what does the research say?
  5. Ventilation and smoke control
  6. Entry, payment and separation between users
  7. Common mistakes, and why they happen
  8. What to require in writing before the plans are finalized
  9. How we do it

A parking garage at the design stage should be built around four decisions: how people enter and pay, how it is ventilated and how smoke is controlled, how electric vehicles are charged, and how users are separated. Each of them determines operating costs, user experience and safety for years. Some of these decisions are cast in concrete and cannot be changed, and some can be deferred. The costly mistake is confusing the two.

What has to be decided now, and what can wait?

A simple working rule: anything inside the structure or under the floor is decided at design. Anything connected to it can be chosen later.

  • Now: the number of lanes and the ramp geometry, clear height, sleeves and conduits in every lane and to every parking space, space for electrical panels and transformers, the location of fans and ventilation openings, and physical separation between zones.
  • Can wait: the barriers themselves, license plate recognition cameras, payment stations, charging stations and the operator.

A garage designed this way can change technology every few years without breaking a floor. A garage designed the other way round stays with the technology of opening day.

Electric vehicle charging: what is mandatory in Israel?

Regulation 7A of the Planning and Building Regulations (Installation of Parking Spaces) requires charging infrastructure in a new multi-unit residential building, meaning six or more apartments in one building of at least two floors. The infrastructure includes a charging panel connected to the grid, conduits from the panel to every parking space of the apartments, and an electrical connection of no less than three kilowatts multiplied by twenty percent of the number of parking spaces. A parking space in a mechanical parking facility is exempt.

Note what the formula says: the minimum connection is enough for only a small share of the vehicles charging at the same time. Without a load management system, the residents' experience will be determined by that minimum.

For non-residential buildings we did not find a similar requirement in the regulations as currently in force, so it is worth checking the requirements with the electrical consultant when the permit application is submitted. In the European Union the direction is clear. The 2024 Energy Performance of Buildings Directive requires all parking spaces in new residential buildings to be prepared for charging. In new offices it requires, from 30 May 2026, a charging point for every two parking spaces.

Charging decisions worth making at design

  • Load management: a system that distributes power between the stations, so that no larger electrical connection than necessary is required.
  • An open protocol: stations and a management system that support OCPP, which was adopted in 2024 as the international standard IEC 63584. That way the operator can be replaced without replacing the stations.
  • Metering and billing: each user pays for their own electricity, not from the common meter.
  • Room to grow: space reserved for panels and transformers, as the number of vehicles increases.
  • Who operates: an external provider or the management company, and who is responsible for faults.

Fire safety in charging: what does the research say?

The European Commission's Sustainable Transport Forum published in 2025 guidance on fire safety for charging in covered car parks. According to the review, existing studies do not show that an electric vehicle is more likely to catch fire than a petrol or diesel vehicle. But a lithium battery fire has its own characteristics, such as the risk of reignition after extinguishing, and extinguishing it often takes longer.

The recommendations relevant to design:

  • Charging stations close to the garage entrance and exit, so firefighters can reach them quickly, and away from emergency exits.
  • Emergency shutdown of all stations, automatic and manual, from a central location such as the fire detection panel.
  • A residual current device and overcurrent protection for every station, surge protection, and marked shutdown buttons.
  • Protection against vehicle impact, and stations on a non-combustible surface.
  • Clear signage, and staff training on the location of the stations and the shutdown procedure.

In Israel, the location of the stations and the safety measures are coordinated with the safety consultant and approved by the fire authority. It is worth bringing these recommendations to the table before the plan is submitted, not after.

Ventilation and smoke control

Ventilating an underground parking garage is one of the largest consumers of electricity in the common areas. Sensor-based control runs the fans only when needed. In Israel, ventilation and smoke extraction requirements are set in the Planning and Building Regulations and in the directives of the Fire and Rescue Commissioner, and are approved by the fire authority.

A good example of how to word a control requirement is the California Energy Code. It requires ventilation to be reduced to half of the design rate or less when there is no pollution, and sensors to be deployed at a defined density. The sensors need manufacturer certification for accuracy and drift, and when a sensor is faulty or has not been calibrated on time, the system reverts to full ventilation and raises an alert.

From a maintenance perspective, this means three things:

  • The sensors need calibration. Place them where they are accessible, and budget for periodic calibration according to the manufacturer's instructions.
  • Not only carbon monoxide. Diesel engines emit relatively little carbon monoxide and a lot of nitrogen oxides. In a garage with service and delivery vehicles, it is worth adding NO2 sensors as well. The European standard EN 50545-1 covers detectors for both gases.
  • Interfaces get tested. Plan how to carry out periodic testing of the smoke extraction system, its interface with the detection panel and with the regular controls, without shutting down the whole garage. Make sure the operating scenarios are documented and handed over to the operations team.

Entry, payment and separation between users

  • A number of lanes that prevents a queue onto the street at peak hour, and waiting space before the barrier within the plot.
  • Power and communications planned for the payment stations, near the exit and at the elevators.
  • License plate recognition cameras with the right lighting and camera angle, and a procedure for a vehicle that was not recognized.
  • In a mixed-use complex: separate zones and permissions for residents, tenants, visitors and suppliers. Such separation prevents parking in other people's spaces, and makes it possible to allocate expenses fairly.
  • Floor and zone signage in colors and numbers, clear height signage before every entrance, and marked pedestrian routes.

Common mistakes, and why they happen

  1. Fans on a timer, without sensors. It is the cheap solution at construction, and the electricity bill does not appear in the construction budget. The price: unnecessary electricity consumption in every hour the garage is empty.
  2. Sensors nobody calibrates. Calibration was not included in the service contract. The price: ventilation that does not respond to pollution, or fans that run all the time.
  3. Charging infrastructure at the minimum, without load management. The goal was to meet the regulation, not to serve the residents. The price: upgrading the electrical connection after occupancy, across the whole building.
  4. Stations on a closed protocol. The supplier offered the stations and the system as a package. The price: the operator cannot be replaced without replacing all the stations.
  5. Charging from the common meter. It looks simple at first. The price: the whole building pays for private charging, and a dispute that lands with the management company.

What to require in writing before the plans are finalized

  • "The charging infrastructure shall include a load management system, and separate metering for each user."
  • "The charging stations and the management system shall support the OCPP protocol."
  • "An emergency shutdown plan for the charging stations shall be submitted, coordinated with the safety consultant."
  • "The ventilation control shall revert to full ventilation and raise an alert on any sensor fault, and the calibration instructions shall be handed over to the owners."
  • "A procedure for periodic testing of the smoke extraction system shall be designed and documented, one that does not require shutting down the whole garage."

How we do it

At the design stage we build the garage's maintenance budget estimate, including energy, service contracts and inspections. We review the barrier, payment and charging suppliers from a maintenance perspective: warranty, spare parts and local service. When we also manage the garage after occupancy, the decisions made at design are tested by us on site.

Planning a parking garage in an office building, a retail complex or a residential tower? Read about maintenance consulting at the construction stage and about parking management. For the inspections the garage will require after opening, see mandatory parking garage inspections.

Talk to us

We'd love to get to know your property

A short call to understand what you need, a site visit, and a detailed itemized proposal. No sales pressure and no commitment.

  • An itemized proposalCleaning, maintenance, security and management, each priced separately, so you can really compare.
  • A free site visitThe survey we make during the visit is yours to keep, even if you choose another company.
  • An answer within two business daysUrgent fault? Our service center is open 24/7 at +972-3-7736777.
Phone+972-3-7736777Emailoffice@achlagroup.com
HoursSun–Thu 08:00–17:00 · 24/7 service center

Leave your details

Fields marked are required. The rest help us come prepared.

Your details are used only to handle your inquiry and are not given to others for their own use. Privacy policy