Estimating the Maintenance Budget at the Design Stage: How to Build It Before There Is a Building

By Ofek Sela, VP Marketing · · 7 min read

A developer and a maintenance consultant reviewing MEP drawings and a budget spreadsheet, with a crane and building frame outside
In this article 9 topics
  1. Why does the developer need this number now?
  2. What is required in Israel, and what is done elsewhere?
  3. How is the estimate built, step by step?
  4. Where do you get a service life for a component that is not yet installed?
  5. How does the estimate affect the design decisions themselves?
  6. How accurate does the estimate need to be at each stage?
  7. Common mistakes, and why they happen
  8. What to require in writing from whoever builds your estimate
  9. How we do it

A design-stage maintenance budget estimate is an assessment of a building's annual operating cost, built from the drawings and specifications before the building exists. It is built line by line from the inventory of systems, tasks and areas, not by comparison with a neighboring project.

Without such an estimate, the management fees stated in the sale agreements are a guess. And the developer pays for that guess twice: once with disappointed buyers, and once directly, on every unit not yet sold.

Why does the developer need this number now?

There are three practical reasons. First, buyers ask about management fees as early as the sales conversation, and the number they are told becomes their reference point. Second, on unsold units the developer bears its share of the expenses as the owner, so a wrong budget hurts it directly.

The third reason is the important one. At the design stage it is still possible to change the decisions that set operating costs for years: the facade cleaning method, car park ventilation, the extent of the staffed lobby, the type of systems. Once the concrete is poured, all that is left is to pay.

What is required in Israel, and what is done elsewhere?

Israel's Sale Law (Apartments) requires the seller to attach to the contract a specification and maintenance and use instructions. If the developer's bylaws change the share of expenses compared with the standard bylaws (the default bylaws set out in the law), the developer must disclose this in the contract. The law does not set out how to build a budget estimate, so the quality of the estimate depends on professional practice.

Other jurisdictions have made it an obligation. In New South Wales (NSW), Australia, the developer must give the owners, before the first general meeting, an initial maintenance plan and a forecast of the management fees for the first year.

In a building of three storeys or more, an independent reviewer must approve the plan and also confirm that the forecast covers the real expenses. The purpose: a developer should not show fees that are too low in order to sell. The details are in the NSW Government guide to the changes in strata (condominium) law.

Florida tightened the rules for condominium buildings following the collapse of the Surfside tower in 2021. Today, an owners' association still controlled by the developer may not waive or reduce reserve contributions before control is handed over to the owners. The message from both places is the same: a developer estimate that is too low is a known problem, which is why an external review is required.

How is the estimate built, step by step?

  1. Component register. Go through the electrical, HVAC, plumbing, safety and elevator drawings, and record every component: quantity, location and estimated model. It is best to organize it by a fixed classification, so the same register later serves the Tik Mitkan (the facility file) and the maintenance management system.
  2. Tasks and frequencies. For each component, record the servicing the manufacturer requires to keep the warranty valid, and the periodic inspections required by law. In the UK a standard maintenance task library, SFG20, is used for this, and the idea is worth adopting: a written task list, not a general estimate.
  3. Areas and hours. Measure the lobby, corridors, car park, landscaping and facade glazing. Cleaning, landscaping and security hours are derived from the areas and the service level.
  4. Common property energy. Estimate actual operating hours: car park lighting, ventilation fans, pumps, elevators and lobby air conditioning. This is where the difference between sensor-based control and continuous operation shows up in the number.
  5. Staffing model. Which roles are on site, at what hours, and what is provided by an external supplier.
  6. Replacement reserve. For each major component, estimate the service life and spread the future replacement cost over the years. The reserve appears as a separate line, so it is not swallowed up by the operating budget.

Where do you get a service life for a component that is not yet installed?

A good starting point is professional service life tables, such as the economic life tables of CIBSE, the UK's Chartered Institution of Building Services Engineers. Their new version includes a tool that adjusts the value to actual conditions, using factors such as the external and internal environment, the maintenance level and operating hours.

This is the same logic as the "factor method" in the ISO 15686 series of standards: take a reference service life and adjust it for the quality of the component, design, workmanship, environment, conditions of use and maintenance. A rooftop air conditioning unit facing the sea and running around the clock will not last as long as an identical unit in the basement of an office building.

How does the estimate affect the design decisions themselves?

The ISO 15686-5 standard defines life cycle cost analysis: alternatives are compared on all their costs over an agreed analysis period, not only on purchase price. To make a cost today comparable with a cost ten years from now, both are discounted to present value. At the design stage, this is the right tool for the decisions that set management fees.

  • A chiller selected on full-load efficiency alone, when for most hours of the year it will run at part load. The right comparison is on expected annual consumption.
  • Facade cleaning: a permanent rooftop installation versus rope access. The method is set in the architectural design, and it determines the cost of every cleaning over the life of the building.
  • Car park ventilation: continuous operation versus control by pollution detectors. The difference accumulates every year.
  • Imported equipment with no local service representative: cheap to buy, expensive at every fault, and long in downtime.

How accurate does the estimate need to be at each stage?

A concept-stage estimate cannot be accurate, and that is fine. What matters is marking, for each line, where the number came from: measured from the drawings, assumed from a service level, or copied from a similar building. As the design advances, lines move from "assumed" to "measured".

It is also worth building three scenarios over time: the warranty years, when part of the service is included; the first year after the warranty, when service contracts go up; and a long-term steady state. Buyers remember the first year, but the building lives in the third.

Finally, run a sensitivity check: which five assumptions move the number more than all the others. In most projects these are the staffed lobby hours, the extent of security, cleaning frequency, car park energy and the amenities. These are the decisions the developer needs to make consciously.

Common mistakes, and why they happen

  1. Copying management fees from a neighboring project. This happens because it is quick and feels safe for marketing. In practice, a staffed lobby, a pool or a deep underground car park change the number fundamentally, and the gap only shows up after occupancy.
  2. An estimate that is not updated after specification changes. A gym is added or a system is replaced, but the estimate stays at the concept stage. The number in the agreement no longer describes the building that was actually built.
  3. A budget built only on the warranty years. In the first years it looks excellent, and then service contracts go up all at once. Buyers see the increase as a broken promise.
  4. No replacement reserve. It lowers the monthly number and looks good in sales. When a pump, a control panel or air conditioning equipment reaches the end of its life, the replacement lands as a special levy, and from there it is a short way to a dispute.
  5. Forgetting the unsold units. The building runs at full capacity from day one, even when some units are empty. A developer who did not plan for this in advance discovers its share in the cash flow.

What to require in writing from whoever builds your estimate

  • "The estimate will be submitted line by line, with the component register it is based on, and not as a lump sum."
  • "For each line, the source of the number will be stated: measured from the drawings, an assumption based on service level, or a comparison."
  • "Three scenarios will be presented: the warranty years, the first year after them, and steady state."
  • "The replacement reserve will be shown separately, with the service life assumed for each major component and its source."
  • "A sensitivity analysis of the five most influential assumptions will be attached, together with a list of design decisions that change the number."
  • "In a mixed-use complex, expenses will be split by use: residential, retail, offices and car park."
  • "The estimate will be updated after the system suppliers are selected, before the wording of the sale agreement is finalized and before occupancy."

How we do it

We build the maintenance budget estimate at the design stage, from the drawings and specifications, and review system suppliers from a maintenance perspective: warranty, spare parts and local service. When we also manage the building after occupancy, we test the estimate's assumptions against reality ourselves. After occupancy, a detailed expense report arrives every month by the 10th, line by line, and it can be compared with the estimate.

Is your building at the design stage? Read about maintenance consulting during construction, and about what actually goes into building management fees. For the structure of the annual budget after occupancy, see preparing the building's annual budget.

Talk to us

We'd love to get to know your property

A short call to understand what you need, a site visit, and a detailed itemized proposal. No sales pressure and no commitment.

  • An itemized proposalCleaning, maintenance, security and management, each priced separately, so you can really compare.
  • A free site visitThe survey we make during the visit is yours to keep, even if you choose another company.
  • An answer within two business daysUrgent fault? Our service center is open 24/7 at +972-3-7736777.
Phone+972-3-7736777Emailoffice@achlagroup.com
HoursSun–Thu 08:00–17:00 · 24/7 service center

Leave your details

Fields marked are required. The rest help us come prepared.

Your details are used only to handle your inquiry and are not given to others for their own use. Privacy policy