In this article 9 topics
- Who already checks on site, and what does none of them check?
- What is done elsewhere?
- The five-question test for every item
- Hold points: when the consultant must be on site
- "Equivalent" equipment substitution: a comparison table
- Why is this the right time to fix things?
- Common mistakes: why they happen, and what they cost
- What to ask for in writing
- How we do it
Maintenance supervision during construction means planned site visits by a maintenance consultant, who checks what is being installed from the angle of whoever will maintain it for years. It does not replace engineering supervision. It asks a question that no other party on site is measured on: will it be possible to reach, identify, isolate, replace and work safely? In the UK, designers are required by law to take into account those who will maintain and clean the building. In Israel this happens only if the developer requires it in the contracts and sends someone to check.
Who already checks on site, and what does none of them check?
Under the Planning and Building Regulations (Building Licensing), the designer who submitted the permit application and the sub-designers carry out design supervision (pikuach elyon). They check that the work matches the approved plans, and update plans and specifications to reflect design changes. The inspection institute (machon bakara, the licensed body that reviews construction) carries out construction control, and the person responsible for inspecting the works checks that they were carried out according to the permit and the law. The developer's supervisor checks quality, schedule and budget.
All of these check conformity: to the plan, the permit, the standard and the contract. Piping can be installed exactly according to the plan and still run above a fixed ceiling with no access panel. A pump can be in perfect working order and still sit in a place it cannot be removed from without taking down a wall.
What is done elsewhere?
In the UK, regulation 9 of the CDM Regulations 2015 requires designers to eliminate, so far as is reasonably practicable, foreseeable risks to the safety of those who will maintain or clean the building. A risk that was not eliminated must be reduced, and information about it goes into the building's health and safety file. In other words, the question "how will this window be cleaned?" is the designer's legal duty, not a request from the management company.
The British standard BS 8536:2022, titled "Design, manufacture and construction for operability", recommends involving the operator and the maintenance team early, and extending the commitment of the design and construction team into the period after handover. BSRIA's Soft Landings framework states that during design, proposals are reviewed against the needs of building management and of the users.
In the United States, the commissioning guide of the federal GSA (General Services Administration) requires the commissioning provider to review equipment submittals, paying special attention to substitutions and deviations from the design. The checklists it prepares for the site are meant to convey the owner's concerns about long-term operation to the installers. The lesson is three simple tools: written operating requirements, a review of submittals and substitutions, and site visits at fixed points.
The five-question test for every item
At every visit, each item of equipment or infrastructure goes through five questions. The answer to each one: pass, conditional pass, or fail.
- Reach: is there an access panel below the valve, the air conditioning unit or the junction box? Is there working space around the equipment?
- Identify: is the piping labeled by content and flow direction? Does the valve or panel number match the drawing?
- Isolate: can you shut off a floor, a zone or a single pump without shutting down the whole building?
- Replace: is there a way to remove the largest piece of equipment in the machine room or on the roof, without taking down a wall or a railing?
- Work safely: is there safe access to the roof and the equipment on it, and are there anchor points for work at height and for facade cleaning?
A "fail" on questions 4 or 5 is almost always a finding that must reach the developer before the work continues. That is how you build priorities instead of a long list of comments that all carry the same weight.
Hold points: when the consultant must be on site
- A sample floor or room, before the detail is replicated throughout the building. The GSA recommends setting the mock-up requirements already in the owner's requirements.
- Before ceilings and walls are closed on each floor, including photographing the piping and infrastructure.
- Placement of major equipment in the machine rooms and on the roof.
- Every request to substitute approved equipment.
- Before commissioning, to coordinate the documentation requirements for handover.
Write the hold points into the contract, and schedule them through the supervisor. That way the contractor knows in advance when they are coming, and does not see them as a delay.
"Equivalent" equipment substitution: a comparison table
A contractor offers equivalent equipment, sometimes for a good reason such as availability. The question is: equivalent in what? Before approving, require a table that compares the proposed item with the approved one in eight rows:
- Performance and efficiency at part load, not only at full load.
- Who services the model in Israel, and in which regions.
- Spare parts availability, and which parts are held in local stock.
- The warranty terms, and who actually provides the warranty.
- Compatibility with the building's control system and its communication protocol.
- Dimensions, lifting data and access requirements for servicing.
- Training and documentation in Hebrew or English.
- Similar equipment already operating in the building or in the portfolio.
Why is this the right time to fix things?
Before the ceiling is closed, moving a valve is a short job for one tradesperson. After the finishes, it requires dismantling, painting and cleaning. After occupancy, it also requires coordination with tenants, work outside operating hours and shutting down an area.
The popular 1:5:200 ratio, between construction cost and the cost of maintenance and operation over the building's life, is disputed in the research, and it is not wise to rely on it. The logic itself does not need a number: every stage that passes adds layers and people to the repair. And a problem that is never fixed becomes a permanent cost in every service visit, for the whole life of the building.
Common mistakes: why they happen, and what they cost
- The maintenance consultant is invited only to the handover walk. Their fee looks unnecessary during construction. But on handover day everything is already closed, and every finding means dismantling.
- Equipment substitutions are approved on price and delivery time. Those are the two parameters the project manager is measured on. Service and spare parts come to light years later, when the supplier no longer imports the model.
- Labeling "will be done at the end". At the end there is no time and no budget. It is done in a rush, does not match the drawings, or is not done at all.
- Not photographing before closing. It seems unnecessary while everything is still exposed. Years later, people hunt for piping by breaking open walls.
- Findings are sent straight to the contractor. It looks efficient, but it creates a double chain of command. The contractor receives conflicting instructions, and the supervisor loses control.
What to ask for in writing
From the maintenance consultant
- A visit report after every walk, with numbered findings, photos, a score by the five questions and a recommendation.
- A continuously updated list of open findings, with the developer's decision on each one.
- A written opinion on every equipment substitution, based on the comparison table.
- A list of requirements for the Tik Mitkan (the facility file) and the maintenance file of each system.
From the designers and the contractor, in the contract
- "For each system, the designers will present the means of access, isolation and replacement of the major equipment."
- "Every substitution of approved equipment will be submitted with a comparison table, and will not be carried out before the client's written approval."
- "The contractor will photograph the infrastructure before walls and ceilings are closed, by floor and area, and will hand over the photos as part of the Tik Mitkan."
- "The hold points listed in the appendix will be coordinated in advance through the supervisor."
The decision always stays with the developer, because some changes carry a cost and an impact on the schedule. The consultant's role is to show what not fixing means, over years of operation.
How we do it
We review system suppliers and proposed substitutions from a maintenance angle: warranty, spare parts and local service. At the same time, we build the Tik Mitkan and the maintenance file from the site itself. And when we also manage the building after occupancy, we check every detail as the ones who will have to live with it.
Is your project at the structure or systems stage? This is exactly the time. Read about pre-construction consulting and about the role of a maintenance consultant. And on why a small saving in design costs dearly in operation, see maintenance costs in an office building.