Blog

Vetting Building System Suppliers: Warranty, Spare Parts and Service in Israel, and What to Ask Before You Choose

By Ofek Sela, VP Marketing · · 7 min read

A meeting with an equipment supplier around a pump component, specs and a spare parts catalogue
In this article 10 topics
  1. Why does this decision also belong to whoever will operate the building?
  2. What is mandatory in Israel, and what is common practice elsewhere?
  3. A comparison method: threshold criteria, then weighted scoring
  4. What to ask about the warranty?
  5. How do you spot lock-in to a single supplier?
  6. What should be in the post-warranty service contract?
  7. What to require in training and documentation?
  8. Common mistakes, and why they happen
  9. Clauses to copy into the tender documents
  10. How we do it

Vetting building system suppliers does not end with the price and the technical specification. What determines the cost over the system's life is what happens after installation: who repairs it, whether the spare part is available in Israel, and who holds the passwords and the software.

The right method is to compare suppliers by life cycle cost and by written threshold criteria. The service contract that follows the warranty is closed already in the tender, while you still have bargaining power.

Why does this decision also belong to whoever will operate the building?

The decision on air conditioning, elevators, the generator, pumps, the building management system and access control is made during construction, under schedule and budget pressure. Whoever will operate the building is usually not part of it, and discovers the limitations at the first fault. From that point on, the maintenance cost of the system has already been set.

The international standard ISO 15686-5 defines life cycle costing. Alternatives are compared by all their costs over an agreed analysis period, including maintenance, repairs, replacements and energy, discounted to present value. In supplier selection, this turns the question "who is cheaper" into "who is cheaper over the years we will own the system".

What is mandatory in Israel, and what is common practice elsewhere?

Israel's Sale (Apartments) Law requires the seller to attach to the contract a specification and maintenance and use instructions. In practice, these instructions are written from the documentation of the system suppliers. A supplier that does not hand over full documentation leaves the developer with an incomplete mandatory document.

There are several frameworks elsewhere worth knowing:

  • ASHRAE Guideline 0, the commissioning guideline of the American society of HVAC engineers, is based on the Owner's Project Requirements document. Among other things, it sets out the requirements for operation and maintenance, training and warranty, even before design.
  • BS 8536, a British standard for design and construction geared toward operation. The idea: the building should be designed so that it can be operated and maintained, not just built.
  • EN 13269, a European guideline for preparing maintenance contracts, with a checklist of the clauses such a contract should include.
  • The lift regulations in Europe and the UK require every elevator to be supplied with instructions that include plans and drawings for use, maintenance, inspection, repair, periodic checks and rescue, as well as a logbook for recording repairs. The British text appears in the UK Lifts Regulations.

None of these frameworks is mandatory in Israel. But requirements can be copied from them into the tender, and they give the requirement professional backing against a supplier that objects.

A comparison method: threshold criteria, then weighted scoring

A good comparison has two stages. In the first, threshold criteria: a supplier that fails any one of them is out, regardless of price. In the second, weighted scoring for the suppliers that remain.

Recommended threshold criteria:

  • There is an authorized service provider in Israel for the proposed model, with technicians certified on it.
  • The supplier commits in writing to spare parts availability for a defined period, and to advance notice before production ends.
  • The owners will receive administrator passwords, a backup of the configuration and licenses in their name.
  • The supplier submits a proposal for a service contract for the years after the warranty, together with the purchase bid.

Then you score, with the relative weight of each criterion set before the bids are opened:

  1. Life cycle cost over the analysis period: purchase, service contract, expected parts and energy.
  2. Local service capability: coverage, emergency service, and similar buildings it serves today.
  3. Spare parts: stock in Israel, standard or proprietary parts, end-of-model policy.
  4. Openness: open protocols, and the ability of another service company to work on the system.
  5. Warranty: what is included, when it starts and what voids it.
  6. Documentation and training: what is handed over, in what language, and when.

Setting the relative weights in advance is the important part. When they are set after seeing the prices, the comparison becomes a justification for a decision that has already been made.

What to ask about the warranty?

  • When does the warranty start: from delivery, installation, commissioning or handover? On a long project, a warranty that starts at delivery can end before occupancy.
  • What does it include: parts, labor and call-outs, or parts only?
  • What voids it: work by another party, services not carried out, non-original parts?
  • Who actually provides it: the manufacturer, the importer or the installing contractor? And what happens if one of them drops out of the picture?
  • Can it be transferred to the owners and to the management company?

How do you spot lock-in to a single supplier?

Lock-in happens when only the original supplier can work on the system. It is common in building management systems, access control, fire detection systems and elevators. The result: there is no competition when the service contract is renewed, and the price goes up at every renewal.

In building management systems, the main tool is an open communication protocol. BACnet is such a protocol, and it is defined in the ISO 16484-5 standard. It allows equipment from different manufacturers to talk to each other, so you can change supplier or add equipment without replacing the whole system.

  • Which protocol does the system communicate in, and are all the points available in it, or only some?
  • Will you receive administrator passwords, programming files and a backup of the configuration?
  • Will the software licenses be registered in the owners' name, not the contractor's?
  • For elevators: are the diagnostic tools and software needed for maintenance available to another service company?
  • Can another service company get the training and tools to work on the system?

What should be in the post-warranty service contract?

This contract is worth closing in the tender, together with the purchase. After installation, the supplier knows it is hard to replace, and the price reflects that.

  • Scope: preventive maintenance according to the manufacturer's instructions, breakdown calls, parts, and what is explicitly excluded.
  • A price adjustment mechanism defined in advance for the coming years.
  • A written service report after every visit, and an entry in the system log.
  • The right to terminate the contract with reasonable notice, without losing access to the software, the passwords and the documentation.

What to require in training and documentation?

  • Training for the operations team on routine operation, common faults and resetting, before handover and not after.
  • Operation and maintenance instructions in Hebrew or English, with plans and drawings as is customary for elevators.
  • An equipment list with serial numbers, ready for the Tik Mitkan (the facility file).
  • As-built drawings of the system as actually installed.

Common mistakes, and why they happen

  1. Comparing only the purchase price. That is the number in the construction budget, and the decision maker is measured on it. The maintenance costs fall later on the buyers and on the management company.
  2. Approving "equivalent" equipment without checking who services it. The contractor offers a cheaper alternative under schedule pressure. After handover it turns out there is no service representative for it in Israel, and every fault waits for a part from abroad.
  3. Leaving the service contract until after handover. It looks like someone else's problem. In practice, you lose the only moment when there was competition.
  4. Not checking who holds the passwords and licenses. They stay with the contractor or the installer, and disappear when it leaves the project. Every change to the system becomes a dependency.
  5. Setting the relative weights after seeing the bids. This happens when there is already a favorite. The comparison loses its value, and the decision is hard to defend.

Clauses to copy into the tender documents

  • "The bidder shall attach a proposal for a service contract for the years following the end of the warranty, including a price adjustment mechanism."
  • "The bidder undertakes to ensure the availability of spare parts for the proposed model for a period of ___ years, and to give advance notice of the end of production."
  • "Administrator passwords, programming files, configuration backups and licenses shall be handed over to the owners and registered in their name."
  • "The building management system shall communicate using an open protocol, and all control points shall be accessible through it."
  • "The warranty shall start on the date of handover to the owners, and not on the date of delivery."
  • "The operation and maintenance instructions shall include plans and drawings for maintenance, inspection and repair, and shall be delivered before handover."

How we do it

During construction we review the system suppliers from a maintenance perspective: warranty, spare parts and local service. At the same time we build a maintenance budget estimate, so that the decision is made with a picture of the years after installation, and we prepare the Tik Mitkan. And when we also manage the building after occupancy, we vet every supplier as the people who will be working with it.

About to choose suppliers for a project? Read about pre-construction consulting and the role of a maintenance consultant. And for an example of a system where the service contract determines a great deal, see elevator maintenance.

Talk to us

We'd love to get to know your property

A short call to understand what you need, a site visit, and a detailed itemized proposal. No sales pressure and no commitment.

  • An itemized proposalCleaning, maintenance, security and management, each priced separately, so you can really compare.
  • A free site visitThe survey we make during the visit is yours to keep, even if you choose another company.
  • An answer within two business daysUrgent fault? Our service center is open 24/7 at +972-3-7736777.
Phone+972-3-7736777Emailoffice@achlagroup.com
HoursSun–Thu 08:00–17:00 · 24/7 service center

Leave your details

Fields marked are required. The rest help us come prepared.

Your details are used only to handle your inquiry and are not given to others for their own use. Privacy policy