  1. Why this is the property owner's concern, not only the contractor's
  2. Who counts as a contractor for this purpose
  3. Gate one: is the contractor suitable for the job
  4. Gate two: the certificate of insurance, line by line
  5. Gate three: the work permit, and what it really is
  6. Hot work: three sources, and what to adopt
  7. Gate four: the safety briefing
  8. Supervision during the work
  9. Close-out and sign-off
  10. What to write in the agreement with the contractor
  11. Common mistakes, and why they happen
  12. How we do it

Contractors in an occupied property need to pass four gates before they start work: a check of suitability and qualifications, a valid certificate of insurance, a work permit for the specific job, and a safety briefing. After that come supervision during the work and a signed close-out at the end. A contractor that enters without these gates is a direct risk to the property owner: a fire from welding work, an injured passer-by or a fire suppression system left disabled, all of which roll into a claim and onto the building's policy.

Why this is the property owner's concern, not only the contractor's

Section 15 of Israel's Civil Wrongs Ordinance (the main torts statute) sets a basic rule: whoever commissions work from an independent contractor is not, as a rule, liable for a wrong the contractor commits in the course of the work. But the rule has exceptions: where the commissioning party was negligent in choosing the contractor, interfered in its work in a way that caused the damage, authorized or ratified the act, or was responsible under an enactment for performing the act it handed to the contractor.

In practical terms: an orderly supplier file, with licenses, insurance and permits, is not bureaucracy. It is the proof that you chose the contractor with care. On the other hand, a duty that the law places on the property owner, for example proper maintenance of systems, does not pass to the contractor just because the contractor is the one doing the work.

Abroad, the direction is the same. The British safety regulator, HSE, opens its guide to working with contractors with a simple sentence: both you and the contractor have responsibilities under the law. And the CDM 2015 regulations in the UK define construction work so that it also includes alteration, repair, maintenance and redecoration, and they place duties on the client even for work of this kind.

Who counts as a contractor for this purpose

Anyone who works on the property and is not an employee of the management company: regular service providers, contractors for one-off projects, and also the contractors tenants bring in for works inside their own space. A tenant's contractor walks the same corridors, uses the same electricity and works near the same fire suppression systems, so it passes through the same gates.

Note Israeli law as well: the definition of "construction" in the Work Safety Ordinance also includes alteration, repair and maintenance of a building. Construction work is subject to the Work Safety (Construction Work) Regulations, which require the party carrying out the construction to appoint a work manager and to notify the Safety Administration of the construction activity. For substantial renovation or fit-out work, ask to see the appointment and the notice.

Gate one: is the contractor suitable for the job

The British guidance on working with contractors recommends asking questions before selection, and matching the depth of the check to the level of risk. Here is a version adapted to a property in Israel, worded so it can be copied into a supplier onboarding form:

  • Who manages the work on site, and how is it supervised?
  • Will you use subcontractors? If so, how do you vet them, and who are they?
  • What accidents or safety incidents have you had on similar jobs recently?
  • Do you have a risk assessment or a written method statement for similar work?
  • What training have the workers who will come completed, and in what language?

And in addition, standard qualification checks:

  • Electrical work only by an electrician holding a license of the type suited to the work, under the Electricity Law.
  • Work at height only by adult workers trained by a work-at-height instructor who hold a valid training certificate, under the Work Safety (Work at Height) Regulations as amended from 16 October 2026. On a construction site for which notice of the start of construction work has been given, the instructor must be on behalf of a training institution, a safety officer or a registered work manager.
  • Construction and engineering works by a contractor listed in the Register of Contractors, in the branch and classification suited to the work.
  • Special systems such as elevators, fire detection and suppression or gas, only by those authorized to work on them.

Gate two: the certificate of insurance, line by line

Since December 2019, the certificate of insurance (ishur kiyum bituchim) in Israel has been issued in a uniform format set by the Capital Market Authority. The insurer may not change the wording, and the certificate cannot contradict the policy. In other words, cover that does not exist in the policy will not be created by wording on the certificate.

  • The insured's name and company number match the entity that signed the order, not a sister company.
  • Types of insurance: third party and employers' liability almost always, and contractors' all risks insurance on a construction or renovation project.
  • Limits of liability suited to the scope of the work and its risk, not set by whatever the contractor happened to hold.
  • The insurance period covers the entire duration of the work, including foreseeable delays.
  • The description of the service on the certificate matches what the contractor actually does. A cleaning contractor's insurance is not supposed to cover welding work.
  • Extensions in your favor: in the uniform format they are marked with codes. Check, according to what the agreement requires, that they include for example a waiver of subrogation in favor of the party requesting the certificate, additional insured status for the acts of the insured, and a primary insurance clause.

These requirements are written into the agreement with the contractor, not just requested by email. The property's insurance agent is the right person to check the first certificate from every new supplier. We wrote about the insurance the building itself needs in building insurance.

Gate three: the work permit, and what it really is

The British HSG250 guidance on permit-to-work systems was written for heavy industry, but its principle fits any building. A work permit is not just permission to carry out dangerous work. It is part of a system that determines how the work will be done safely, and passes that information to whoever carries it out.

Which works in a building need a written permit:

  • Hot work: welding, cutting, grinding, tarring.
  • Any work that requires disabling detectors, closing sprinklers or shutting down a fire pump.
  • Work in electrical panels, or any work that requires isolation and lockout.
  • Work on the roof, at height or near open edges.
  • Entry into confined spaces: sewer pits, water tanks, shafts.
  • Drilling or breaking into floors, ceilings and walls that carry services.

What should appear in the permit, according to the structure recommended in HSG250:

  1. A permit number, and a reference to other permits related to the same area.
  2. The exact location and a description of the work, including what is not included in it.
  3. The hazards, and the measures taken. Whoever carried out an isolation or disabling signs that it was done.
  4. The issuer's signature, with the date and the time of validity.
  5. The contractor's signature confirming it understood the work, the hazards and the measures, and explained them to the workers.
  6. Shift handover: who continues, and what is checked before continuing.
  7. Hand-back at completion: the contractor signs that it has finished, and the permit issuer signs that the systems are ready to return to service.
  8. Close-out: confirmation that the systems were checked and returned to normal.

One lesson from the inquiry into the Piper Alpha disaster in the North Sea appears explicitly in the guidance. Suspended permits were kept in the safety office and not in the control room, and whoever took over the shift did not know which equipment was under maintenance. The guidance reminds readers that a suspended permit remains live until it is closed. In a building, the equivalent is the control center: it needs to see at every moment which permits are open, and which detectors are disabled.

Hot work: three sources, and what to adopt

Israel's Institute for Occupational Safety and Hygiene recommends not starting hot work without written approval from the responsible party on site, after a risk assessment. Its checklist includes suitable extinguishing equipment, removing or covering flammable materials, sealing openings through which a spark can pass, and notifying the surroundings.

On the fire watch, the person who watches the area during the work and after it, the sources are not identical. The American OSHA rule for welding and cutting requires a fire watch for at least half an hour after completion, and prefers a written permit. The American NFPA 51B standard extended this in its 2019 edition to at least an hour, and the checklist of the Institute for Occupational Safety and Hygiene also speaks of an hour. Our recommendation: adopt the stricter requirement, and write it into the permit.

If detectors in the area are disabled to prevent a false alarm, record in the permit who disabled them, when, and who restores them to operation. A detector left disabled after the contractor has gone is an area without protection, and nobody knows about it.

Gate four: the safety briefing

A short briefing before the first entry prevents a lot of incidents. It is documented with the signature of every worker, not only the work manager. The HSE stresses particular attention to workers whose first language is different, and that is very true of sites in Israel as well: a briefing the worker did not understand did not happen.

  • Escape routes, the assembly point and the location of extinguishers and fire hydrants.
  • What to do when an alarm goes off, and whom to call.
  • Areas off limits without an escort: electrical rooms, pump rooms, the roof.
  • Working hours, noise hours and which elevator may be used.
  • Protection of public areas and waste removal at the contractor's expense.

Supervision during the work

The British rule is simple: the higher the risk, the more you need to do. Supervision does not mean standing over the contractor all day. It means that someone on behalf of the property walks the site, checks that the work is being done according to the permit, and has written authority to stop it.

  • Whether the workers on site are the ones who were registered and briefed.
  • Whether the protection and fencing are in place, and escape routes are clear.
  • Whether an isolated system is tagged and locked.
  • Whether the work stays within the approved hours and area.

Close-out and sign-off

  1. A joint completion walk, with "after" photos.
  2. Every isolated system has been returned to service and checked: water, electricity, detectors, sprinklers.
  3. The area is clean, and the waste has been removed.
  4. The contractor has handed over certificates, warranties and as-built drawings, and they go into the Tik Mitkan (the facility file).
  5. Only after all of this is the invoice approved for payment.

What to write in the agreement with the contractor

  • "The contractor shall not begin work on the property before presenting a certificate of insurance in the uniform format, including the extensions set out in the insurance appendix."
  • "A subcontractor shall enter the property only with prior written approval, and after presenting its own certificate of insurance or being included in the contractor's insurance."
  • "All hot work, work on fire suppression systems or electrical work shall be carried out only under a work permit signed by property management."
  • "The property's representative may stop the work at any time when it deviates from the permit, without the contractor being entitled to compensation as a result."
  • "The final payment shall be made after a completion walk and the delivery of as-built drawings and certificates."

Common mistakes, and why they happen

  • A certificate of insurance that expires in the middle of the work. This happens when no expiry date is recorded with a reminder. The result: an incident during a period when the contractor is not insured, and the damage moves to the building's policy.
  • A certificate in one company's name and a different subcontractor on site. This happens because the check is done against whoever signed, not against whoever showed up. In a claim, the main contractor's insurer will check whether the subcontractor is covered at all.
  • Tenant contractors who enter without going through property management. This happens because the tenant sees the space as its own. But the sprinkler in its ceiling is connected to the whole building's system.
  • "Small" hot work without a permit. This happens because it is supposed to take a few minutes. It is precisely on a short job that there is no fire watch, and the fire starts after everyone has left.
  • A permit closed without checking that the systems are back in service. This happens when the signing is done in the office and not on site. A disabled detector can stay that way for weeks.
  • Payment before the completion walk. This happens under end-of-month pressure. After payment there is no leverage to demand a repair or as-built drawings.

How we do it

In the properties we manage, a fault that requires a contractor is opened as a call in the management system, and tenants or residents track it in the app until it is closed. Independent quality control checks the work after the contractor, and our service center is available 24/7 if something goes wrong at night. The cost of every job appears in the monthly report that reaches the property owner by the 10th of the month, line by line.

For details see building maintenance and building management and maintenance. On the inspections the building's systems must undergo, read periodic building inspections.

Talk to us

We'd love to get to know your property

A short call to understand what you need, a site visit, and a detailed itemized proposal. No sales pressure and no commitment.

  • An itemized proposalCleaning, maintenance, security and management, each priced separately, so you can really compare.
  • A free site visitThe survey we make during the visit is yours to keep, even if you choose another company.
  • An answer within two business daysUrgent fault? Our service center is open 24/7 at +972-3-7736777.
Phone+972-3-7736777Emailoffice@achlagroup.com
HoursSun–Thu 08:00–17:00 · 24/7 service center

Leave your details

Fields marked are required. The rest help us come prepared.

Your details are used only to handle your inquiry and are not given to others for their own use. Privacy policy